Mississippi Power's QF Power Purchase Contracting Process

  • Generator contacts Mississippi Power’s Renewable Energy Program Manager to discuss Generator’s intent to sell the output from a Qualifying Facility to Mississippi Power pursuant to PURPA.
  • Mississippi Power’s annual avoided cost filings and publicly available historical avoided cost information can be found on the Mississippi Power website.
  • Generator will need to follow the Rate CPE contract requirements to establish a legally enforceable obligation.
  • Once a legally enforceable obligation is established, a Rate CPE contract can be requested.